Engineering SOP -FAT : Factory Acceptance Test & SAT : Site Acceptance Test

-

Factory Acceptance Test (FAT)

  • Inspection and static &/or dynamic testing of system or major system component to support the qualification of an equipment/system conducted & documented at a supplier site
  • Establishing documented evidence that the vendor fabrication process or material and completed equipment meet vendor & customer specifications.
  • The objective of FAT is to verify that the main equipment or system meets design specification and confirm to agreed performance intentions.
  • The tests will be performed & reported by the supplier.
  • All tests perform during FAT must be in accordance with reviewed & approved protocols and procedures.

Minimum acceptance criteria for FAT

The equipments and system shall comply with:

  • URS/DQ and Purchase specifications
  • Design Drawing
  • Engineering diagrams (wherever it’s applicable)
  • Safety rules (wherever it’s applicable)
  • Trial run (wherever it’s applicable)
  • Software requirement to meet 21CFR part 11
  • User Manual
  • Maintenance manual
  • Piping and installation design
  • Electrical schematic
  • Process and utility diagram
  • Documents for welding
  • Spare part list
  • MOC certificates (Material of Construction)

Applicability of FAT procedure

  • FAT shall be performed for modifiable off-the-shelf equipment or machines.
  • Modifiable off-the-shelf: Developed or customized by a vendor to meet specific user requirements.
  • Off-the-shelf: Used “ as is”

Site Acceptance Test (SAT)

  • Inspection & dynamic testing of systems or major system components to support the qualification of an equipment/system conducted at client site.
  • Establishing documented evidence that during receipt of the items / equipment / system at site, conform with the standard laid in the protocol, purchase order and manufacturer specifications.
  • To ensure that the site of installation is ready.

Minimum acceptance criteria for SAT

The items of equipment and system shall comply with:

  • Major component verification as per FAT report and specifications
  • Packing Material list
  • Physical condition of major components or machine
  • Operation testing / verification shall be perform
  • Manufacturer’s machine identification code / identification number.

Minimum document require for SAT

  • User Manual
  • Maintenance manual
  • Process & utility diagram
  • Electrical Schematics
  • Spare parts list
  • FAT report & specifications
  • Design specifications & drawings
  • Safety Rules
  • Qualification documents (if specify)

For any feedback or suggestions write to us at info@pharmastate.com

PharmaState Blog
This is a platform for people working in the pharmaceuticals industry for Discussions, Jobs, News updates, Professional Profile display space and company business pages. PharmaState DNA is having four pillars: Quality, Transparency, Innovation & Benchmarks.

Share this article

Recent posts

Popular categories

Leave a Reply

Recent comments

Business Alnavedic on History of Indian Pharma Industry
Ahmed Mohamed Elkhodragy on MACO Calculation
Jennifer Osunde on DEFECTS IN UNCOATED TABLETS
Vinod on DEVIATION
Rajib ghose on TOOLING FOR TABLETING
K. SRinivasula Reddy on Quality Agreements – PART 2
Sunil Kumar M on SITE ACCEPTANCE TEST (SAT)
Khalid on IQ Protocol
Khalid on IQ Protocol
Nagabooshanam on Calibration of Reactor
PharmaState Blog on SOP for Sampling
Swapnil Khodake on TOOLING FOR TABLETING
%d bloggers like this: